Construction works of the S.Croce di Magliano-Ururi station-Rotello expressway, 1st , 2nd and 3rd Lots – Project no. 5374/1/FESR
Paese
ItalyCliente
Campobasso Local AdministrationFinanziatore
Cassa per il MezzogiornoAssociazione
ing.Guerra,ing.Zaccardi,dr.Scasserra,ing.Amici (members)Periodo
04/1983 - 10/1988Descrizione Progetto
Preliminary and Final Design of an internal road crossing the Molise Region and including the Crocella (44 m), Macchialonga (268 m), Scassa (168 m), Selva 1 (24 m), Selva 2 (24 m), Ripa di Muro (132 m), Lago di Luppolo (217 m) viaducts and the “Rotello” tunnel of 640 lm. The project included topographical surveys, geological-technical study, the design of viaducts and tunnels, and reclamation works of rock slopes with particular interventions. Besides the preparation of Tender Dossier and Documents, the project included the Work Supervision.
Descrizione Servizi
Preliminary and final design of Lots 1, 2 and 3. Works supervision and control of Lot 1.