Layout variant and modernisation of S.S. 125 Primary Road (Sardinia) between km 174+ 500 and 183+100.
Country
ItalyName of Client
ANASFinancing sources
ANASDuration
01/1986 - 01/1987Project Description
Final Design of the variant between km 174+500 and 183+100 of the Primary Road 125. The project concerned a road section crossing a mountainous area and characterised by numerous rock cuts with unstable slopes that required strong reinforcement interventions with reclaiming, tie-beams and reinforcement works. The study included topography, geological and technical survey and analysis, reinforcement work design, a bridge of 600 m, and the preparation of Tender specifications and documents.
Services Description
Detailed Engineering Design.