Drinkable water supply in the towns of Bandundu and Inkisi

Final design and preparation of the tender dossier for the drinkable water supply in the town of Bandundu (365.000 inhabitants) and Inkisi (120.000 inhabitants)

Paese

Dem. Rep. of Congo

Cliente

Bureau Central de Coordination (BCECO)

Finanziatore

IDA

Periodo

04/2004 - 05/2006

Descrizione Progetto

Final design and preparation of the tender dossier for the drinkable water supply in the town of Bandundu (365.000 inhabitants) and Inkisi (120.000 inhabitants).

Descrizione Servizi

Main activities carried out: Socio-economic study; diagnostic study of existing infrastructures; hydrological study; hydrogeological study; preliminary and final design; technical-economical feasibility study; price scale study; final design; production: 4 deep wells 250 m to Bandundu; stocking: 5 high level tanks of 1200 m³ each and 1 half-buried water tank of 1200 m³; 1 pumping station h=150 m (Inkisi); 149 km of pipeline: 88 km to Bandundu and 61 km to Inkisi; bid documentation preparation.