Supervision of works for the reconstruction of priority sections on the Kampala-Mbarara road (Northern Corridor): Package A: Busega-Nsangi and Kamengo-Lukaya
Country
UgandaName of Client
UNRAFinancing sources
Government of UgandaAssociation
TECHNITAL SpA (Italy) (member) – SABA Engineering Plc (Ethiopia) (member)Duration
01/2009 - 06/2012Project Description
The works concern the following section: Package A – Busega-Nsangi (12 km) and Kamengo-Lukaya (51 km) between Kampala and Masaka.
Rehabilitation of the carriageway (widening to 11 meters), including the construction of 11 meters of sub-base (17 cm) and base (25 cm) in graded aggregates; the construction of 7 meters of asphalt base (DBM) of 10 cm and asphalt concrete coating of 5 cm; and a surface dressing treatment of shoulders.
The works included also urban crossings and swamps treatment in rockfill.
Services Description
The services carried out are: Design review; Works supervision for the reconstruction of priority sections on the Kampala-Mbarara road.