Salerno-Reggio Calabria motorway

Salerno-Reggio Calabria Motorway. Adjustment works to type I a) Regulation CNR/80, Section 3°, part 1°, Lot 2° between km 320+400 and 331+400 (connection between Lamezia Terme - bridge over the stream Randace). Preliminary and final design of the emergency lane.

Country

Italy

Name of Client

ANAS-Azienda Nazionale Autonoma delle Strade

Financing sources

ANAS-Azienda Nazionale Autonoma delle Strade

Association

AIC Progetti (Leader) -Studio Ing. Fabio Cesaroni-Studio Ing. Carlo Cassinis (geotechnician) – Studio Karrer/Lacava (environmental impact) (members)

Duration

07/1996 - 01/1997

Project Description

The study included topographical surveys, geognostical surveys, non-destructive tests on existing structures, the definition of environmental impact works.
The design included new underpasses and widening and rehabilitation of Amato and Turrina bridges and of 8 minor bridges, besides superstructure and pavement, and the location of borrow pits and material deposits. Moreover, the project included technical specifications and tender documents drawing out.

Services Description

Topographical survey - Geological survey - Geotechnical study - Environmental impact study - Preliminary and final design